Demonstration data — not a live contract.
All contracts

Specimen EPC contract

Generic EPC

44 obligations

ClauseObligationPartyCategoryPeriodTime barStatusReviewed byNext due
1.2Notify change of address within 7 daysEither partyNotice7 calendar daysNoConfirmedSpecimen answer key–
2.1Give Contractor Site access within 30 daysEmployerOther30 calendar daysNoConfirmedSpecimen answer key–
2.2Provide evidence of funding within 21 daysEmployerSubmission21 calendar daysNoConfirmedSpecimen answer key–
3.1Name Employer's Representative within 10 daysEmployerNotice10 calendar daysNoEditedSpecimen answer key–
3.2Give 14 days' notice before replacing RepresentativeEmployerNotice14 calendar daysNoConfirmedSpecimen answer key–
3.3Answer request for decision within 14 daysEngineerApproval14 calendar daysNoEditedSpecimen answer key–
4.1Deliver Performance Security within 28 daysContractorSecurity28 calendar daysNoConfirmedSpecimen answer key2026-11-10
4.2Extend Performance Security before expiryContractorSecurity30 calendar daysNoConfirmedSpecimen answer key–
4.3Submit Key Personnel details within 15 daysContractorSubmission15 calendar daysNoConfirmedSpecimen answer key2026-10-28
4.4Notify proposed Subcontractor 21 days before startContractorNotice21 calendar daysNoConfirmedSpecimen answer key–
5.1Submit design delivery schedule within 20 daysContractorProgramme20 calendar daysNoEditedSpecimen answer key2026-11-02
5.2Notify error in Employer's Requirements within 10 daysContractorNotice10 calendar daysYesConfirmedSpecimen answer key–
5.3Hand over as-built documents 45 days before Completion TestsContractorSubmission45 calendar daysNoConfirmedSpecimen answer key–
6.1Send site safety report every 30 daysContractorSubmissionNo stated periodNoEditedSpecimen answer key–
6.2Report serious accident within 2 working daysContractorNotice2 working daysNoConfirmedSpecimen answer key–
7.1Give 5 working days' notice before covering workContractorNotice5 working daysNoConfirmedSpecimen answer key–
7.2Replace or repair rejected Plant within 30 daysContractorDefects30 calendar daysNoConfirmedSpecimen answer key–
8.1Begin Works within 14 days of Commencement DateContractorCompletion14 calendar daysNoConfirmedSpecimen answer key2026-10-27
8.2Submit detailed programme within 28 daysContractorProgramme28 calendar daysNoEditedSpecimen answer key–
8.3Deliver progress report every 30 daysContractorProgrammeNo stated periodNoEditedSpecimen answer key2026-11-12
8.5Warn of delay within 7 days of learningContractorNotice7 calendar daysNoConfirmedSpecimen answer key2026-11-06
8.6Give 21 days' notice before suspending workContractorNotice21 calendar daysNoConfirmedSpecimen answer key–
9.1Give 21 days' notice of readiness for Tests on CompletionContractorTesting21 calendar daysNoEditedSpecimen answer key–
9.2Repeat failed test within 14 days of requestContractorTesting14 calendar daysNoConfirmedSpecimen answer key–
10.1Issue Taking-Over Certificate or give reasons within 21 daysEngineerCompletion21 calendar daysNoEditedSpecimen answer key–
11.1Remedy notified defect within 14 daysContractorDefects14 calendar daysNoConfirmedSpecimen answer key–
11.2Issue Performance Certificate within 28 days after DNPEngineerDefects28 calendar daysNoEditedSpecimen answer key–
12.1Submit variation proposal within 14 daysContractorVariation14 calendar daysNoConfirmedSpecimen answer key2026-11-07
12.2Object to instruction as Variation within 10 daysContractorVariation10 calendar daysYesEditedSpecimen answer key2026-11-03
13.1Pay advance payment within 30 daysEmployerPayment30 calendar daysNoConfirmedSpecimen answer key–
13.2Submit payment application every 30 daysContractorPaymentNo stated periodNoEditedSpecimen answer key–
13.3Certify payment application within 21 daysEngineerPayment21 calendar daysNoEditedSpecimen answer key–
13.4Pay certified amount within 45 daysEmployerPayment45 calendar daysNoConfirmedSpecimen answer key–
13.5Submit draft final statement within 56 daysContractorPayment56 calendar daysNoEditedSpecimen answer key–
14.1Correct material breach within 30 daysContractorOther30 calendar daysNoConfirmedSpecimen answer key–
14.2Give 28 days' notice to terminateContractorNotice28 calendar daysNoConfirmedSpecimen answer key–
15.1Deliver evidence of insurances within 21 daysContractorInsurance21 calendar daysNoConfirmedSpecimen answer key2026-11-03
15.2Deliver evidence of insurance renewal 7 days before expiryContractorInsurance7 calendar daysNoConfirmedSpecimen answer key–
16.1Notify Force Majeure within 14 daysEither partyNotice14 calendar daysYesConfirmedSpecimen answer key–
17.1Notify claim for additional time or money within 28 daysContractorClaim28 calendar daysYesConfirmedSpecimen answer key2026-11-27
17.2Send full particulars of claim within 42 daysContractorClaim42 calendar daysNoEditedSpecimen answer key2026-12-11
17.3Respond to claim particulars within 42 daysEngineerClaim42 calendar daysNoEditedSpecimen answer key–
17.4Give notice of dissatisfaction within 28 daysEither partyDispute28 calendar daysYesEditedSpecimen answer key–
17.5Attempt amicable settlement for 30 daysEither partyDispute30 calendar daysNoConfirmedSpecimen answer key–