Clause 4.2

Extend Performance Security before expiry

Where the Performance Security would expire before the Works are complete, the Contractor must extend it not later than 30 days before its expiry date.

Party who must act
Contractor
Other party
Employer
Category
Security
Trigger type
Event
Period
30 calendar days, before the trigger
Time bar
No
Trigger event
Expiry date of the Performance Security (where it would expire before completion of the Works)
Keys: C confirm, E edit, R reject

Clause 4.2

Keeping the security valid

Where the Performance Security would expire before the Works are complete, the Contractor shall extend it not later than 30 days before its expiry date.