Detailed programme for reviewOct 29, 2026Outgoing, Contractor to Engineer, OUT-0001Satisfies: 8.2 Submit detailed programme within 28 daysDeadline of Nov 10, 2026 metRemove linkLink to an obligation or due dateChoose one1.2 Notify change of address within 7 days2.1 Give Contractor Site access within 30 days2.2 Provide evidence of funding within 21 days3.1 Name Employer's Representative within 10 days3.2 Give 14 days' notice before replacing Representative3.3 Answer request for decision within 14 days4.1 Deliver Performance Security within 28 days4.1 Deliver Performance Security within 28 days, due Nov 10, 20264.2 Extend Performance Security before expiry4.3 Submit Key Personnel details within 15 days4.3 Submit Key Personnel details within 15 days, due Oct 28, 20264.4 Notify proposed Subcontractor 21 days before start5.1 Submit design delivery schedule within 20 days5.1 Submit design delivery schedule within 20 days, due Nov 2, 20265.2 Notify error in Employer's Requirements within 10 days5.3 Hand over as-built documents 45 days before Completion Tests6.1 Send site safety report every 30 days6.2 Report serious accident within 2 working days7.1 Give 5 working days' notice before covering work7.2 Replace or repair rejected Plant within 30 days8.1 Begin Works within 14 days of Commencement Date8.1 Begin Works within 14 days of Commencement Date, due Oct 27, 20268.2 Submit detailed programme within 28 days8.2 Submit detailed programme within 28 days, due Nov 10, 20268.3 Deliver progress report every 30 days8.3 Deliver progress report every 30 days, due Nov 12, 20268.3 Deliver progress report every 30 days, due Dec 12, 20268.3 Deliver progress report every 30 days, due Jan 11, 20278.3 Deliver progress report every 30 days, due Feb 10, 20278.3 Deliver progress report every 30 days, due Mar 12, 20278.3 Deliver progress report every 30 days, due Apr 11, 20278.3 Deliver progress report every 30 days, due May 11, 20278.3 Deliver progress report every 30 days, due Jun 10, 20278.3 Deliver progress report every 30 days, due Jul 10, 20278.3 Deliver progress report every 30 days, due Aug 9, 20278.3 Deliver progress report every 30 days, due Sep 8, 20278.3 Deliver progress report every 30 days, due Oct 8, 20278.3 Deliver progress report every 30 days, due Nov 7, 20278.3 Deliver progress report every 30 days, due Dec 7, 20278.3 Deliver progress report every 30 days, due Jan 6, 20288.3 Deliver progress report every 30 days, due Feb 5, 20288.3 Deliver progress report every 30 days, due Mar 6, 20288.3 Deliver progress report every 30 days, due Apr 5, 20288.5 Warn of delay within 7 days of learning8.5 Warn of delay within 7 days of learning, due Nov 6, 20268.6 Give 21 days' notice before suspending work9.1 Give 21 days' notice of readiness for Tests on Completion9.2 Repeat failed test within 14 days of request10.1 Issue Taking-Over Certificate or give reasons within 21 days11.1 Remedy notified defect within 14 days11.2 Issue Performance Certificate within 28 days after DNP12.1 Submit variation proposal within 14 days12.1 Submit variation proposal within 14 days, due Nov 7, 202612.2 Object to instruction as Variation within 10 days12.2 Object to instruction as Variation within 10 days, due Nov 3, 202613.1 Pay advance payment within 30 days13.2 Submit payment application every 30 days13.3 Certify payment application within 21 days13.4 Pay certified amount within 45 days13.5 Submit draft final statement within 56 days14.1 Correct material breach within 30 days14.2 Give 28 days' notice to terminate15.1 Deliver evidence of insurances within 21 days15.1 Deliver evidence of insurances within 21 days, due Nov 3, 202615.2 Deliver evidence of insurance renewal 7 days before expiry16.1 Notify Force Majeure within 14 days17.1 Notify claim for additional time or money within 28 days17.1 Notify claim for additional time or money within 28 days, due Nov 27, 202617.2 Send full particulars of claim within 42 days17.2 Send full particulars of claim within 42 days, due Dec 11, 202617.3 Respond to claim particulars within 42 days17.4 Give notice of dissatisfaction within 28 days17.5 Attempt amicable settlement for 30 daysRelationSatisfiesRefers toResponds toDisputesLinkDelete letter