Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 9.1
Give 21 days' notice of readiness for Tests on Completion
The Contractor must give the Employer's Representative at least 21 days' notice of the date on which it will be ready for the Tests on Completion.
- Party who must act
- Contractor
- Other party
- Engineer
- Category
- Testing
- Trigger type
- Event
- Period
- 21 calendar days, before the trigger
- Time bar
- No
- Trigger event
- Contractor becomes ready for the Tests on Completion
Keys: C confirm, E edit, R reject
Clause 9.1
Notice of readiness
The Contractor shall give the Employer's Representative at least 21 days' notice of the date on which it will be ready for the Tests on Completion.