Specimen EPC contract
EPC générique
44 obligations
| Clause | Obligation | Partie | Catégorie | Délai | Forclusion | Statut | Revu par | Prochaine échéance |
|---|---|---|---|---|---|---|---|---|
| 1.2 | Notify change of address within 7 days | L’une ou l’autre partie | Notification | 7 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 2.1 | Give Contractor Site access within 30 days | Maître d’ouvrage | Autre | 30 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 2.2 | Provide evidence of funding within 21 days | Maître d’ouvrage | Remise de document | 21 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 3.1 | Name Employer's Representative within 10 days | Maître d’ouvrage | Notification | 10 jours calendaires | Non | Modifiée | Specimen answer key | – |
| 3.2 | Give 14 days' notice before replacing Representative | Maître d’ouvrage | Notification | 14 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 3.3 | Answer request for decision within 14 days | Maître d’œuvre | Approbation | 14 jours calendaires | Non | Modifiée | Specimen answer key | – |
| 4.1 | Deliver Performance Security within 28 days | Entrepreneur | Garantie | 28 jours calendaires | Non | Confirmée | Specimen answer key | 2026-11-10 |
| 4.2 | Extend Performance Security before expiry | Entrepreneur | Garantie | 30 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 4.3 | Submit Key Personnel details within 15 days | Entrepreneur | Remise de document | 15 jours calendaires | Non | Confirmée | Specimen answer key | 2026-10-28 |
| 4.4 | Notify proposed Subcontractor 21 days before start | Entrepreneur | Notification | 21 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 5.1 | Submit design delivery schedule within 20 days | Entrepreneur | Programme | 20 jours calendaires | Non | Modifiée | Specimen answer key | 2026-11-02 |
| 5.2 | Notify error in Employer's Requirements within 10 days | Entrepreneur | Notification | 10 jours calendaires | Oui | Confirmée | Specimen answer key | – |
| 5.3 | Hand over as-built documents 45 days before Completion Tests | Entrepreneur | Remise de document | 45 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 6.1 | Send site safety report every 30 days | Entrepreneur | Remise de document | Aucun délai indiqué | Non | Modifiée | Specimen answer key | – |
| 6.2 | Report serious accident within 2 working days | Entrepreneur | Notification | 2 jours ouvrables | Non | Confirmée | Specimen answer key | – |
| 7.1 | Give 5 working days' notice before covering work | Entrepreneur | Notification | 5 jours ouvrables | Non | Confirmée | Specimen answer key | – |
| 7.2 | Replace or repair rejected Plant within 30 days | Entrepreneur | Malfaçons | 30 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 8.1 | Begin Works within 14 days of Commencement Date | Entrepreneur | Achèvement | 14 jours calendaires | Non | Confirmée | Specimen answer key | 2026-10-27 |
| 8.2 | Submit detailed programme within 28 days | Entrepreneur | Programme | 28 jours calendaires | Non | Modifiée | Specimen answer key | – |
| 8.3 | Deliver progress report every 30 days | Entrepreneur | Programme | Aucun délai indiqué | Non | Modifiée | Specimen answer key | 2026-11-12 |
| 8.5 | Warn of delay within 7 days of learning | Entrepreneur | Notification | 7 jours calendaires | Non | Confirmée | Specimen answer key | 2026-11-06 |
| 8.6 | Give 21 days' notice before suspending work | Entrepreneur | Notification | 21 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 9.1 | Give 21 days' notice of readiness for Tests on Completion | Entrepreneur | Essais | 21 jours calendaires | Non | Modifiée | Specimen answer key | – |
| 9.2 | Repeat failed test within 14 days of request | Entrepreneur | Essais | 14 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 10.1 | Issue Taking-Over Certificate or give reasons within 21 days | Maître d’œuvre | Achèvement | 21 jours calendaires | Non | Modifiée | Specimen answer key | – |
| 11.1 | Remedy notified defect within 14 days | Entrepreneur | Malfaçons | 14 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 11.2 | Issue Performance Certificate within 28 days after DNP | Maître d’œuvre | Malfaçons | 28 jours calendaires | Non | Modifiée | Specimen answer key | – |
| 12.1 | Submit variation proposal within 14 days | Entrepreneur | Modification | 14 jours calendaires | Non | Confirmée | Specimen answer key | 2026-11-07 |
| 12.2 | Object to instruction as Variation within 10 days | Entrepreneur | Modification | 10 jours calendaires | Oui | Modifiée | Specimen answer key | 2026-11-03 |
| 13.1 | Pay advance payment within 30 days | Maître d’ouvrage | Paiement | 30 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 13.2 | Submit payment application every 30 days | Entrepreneur | Paiement | Aucun délai indiqué | Non | Modifiée | Specimen answer key | – |
| 13.3 | Certify payment application within 21 days | Maître d’œuvre | Paiement | 21 jours calendaires | Non | Modifiée | Specimen answer key | – |
| 13.4 | Pay certified amount within 45 days | Maître d’ouvrage | Paiement | 45 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 13.5 | Submit draft final statement within 56 days | Entrepreneur | Paiement | 56 jours calendaires | Non | Modifiée | Specimen answer key | – |
| 14.1 | Correct material breach within 30 days | Entrepreneur | Autre | 30 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 14.2 | Give 28 days' notice to terminate | Entrepreneur | Notification | 28 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 15.1 | Deliver evidence of insurances within 21 days | Entrepreneur | Assurance | 21 jours calendaires | Non | Confirmée | Specimen answer key | 2026-11-03 |
| 15.2 | Deliver evidence of insurance renewal 7 days before expiry | Entrepreneur | Assurance | 7 jours calendaires | Non | Confirmée | Specimen answer key | – |
| 16.1 | Notify Force Majeure within 14 days | L’une ou l’autre partie | Notification | 14 jours calendaires | Oui | Confirmée | Specimen answer key | – |
| 17.1 | Notify claim for additional time or money within 28 days | Entrepreneur | Réclamation | 28 jours calendaires | Oui | Confirmée | Specimen answer key | 2026-11-27 |
| 17.2 | Send full particulars of claim within 42 days | Entrepreneur | Réclamation | 42 jours calendaires | Non | Modifiée | Specimen answer key | 2026-12-11 |
| 17.3 | Respond to claim particulars within 42 days | Maître d’œuvre | Réclamation | 42 jours calendaires | Non | Modifiée | Specimen answer key | – |
| 17.4 | Give notice of dissatisfaction within 28 days | L’une ou l’autre partie | Différend | 28 jours calendaires | Oui | Modifiée | Specimen answer key | – |
| 17.5 | Attempt amicable settlement for 30 days | L’une ou l’autre partie | Différend | 30 jours calendaires | Non | Confirmée | Specimen answer key | – |