Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 13.5
Submit draft final statement within 56 days
The Contractor shall submit a draft final statement within 56 days after receiving the Performance Certificate.
- Party who must act
- Contractor
- Other party
- Employer
- Category
- Payment
- Trigger type
- Event
- Period
- 56 calendar days, after the trigger
- Time bar
- No
- Trigger event
- Contractor receives the Performance Certificate
Keys: C confirm, E edit, R reject
Clause 13.5
Final statement
The Contractor shall submit a draft final statement within 56 days after receiving the Performance Certificate.