Clause 13.5

Submit draft final statement within 56 days

The Contractor shall submit a draft final statement within 56 days after receiving the Performance Certificate.

Party who must act
Contractor
Other party
Employer
Category
Payment
Trigger type
Event
Period
56 calendar days, after the trigger
Time bar
No
Trigger event
Contractor receives the Performance Certificate