Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 17.2
Send full particulars of claim within 42 days
Within 42 days of becoming aware of the event, the Contractor must send the Employer's Representative full particulars of the claim.
- Party who must act
- Contractor
- Other party
- Engineer
- Category
- Claim
- Trigger type
- Event
- Period
- 42 calendar days, after the trigger
- Time bar
- No
- Trigger event
- Contractor becomes aware of the event giving rise to the claim
Keys: C confirm, E edit, R reject
Clause 17.2
Particulars of a claim
Within 42 days of becoming aware of the event, the Contractor shall send the Employer's Representative full particulars of the claim.