45 of 45 reviewed

Clause 17.2

Send full particulars of claim within 42 days

Within 42 days of becoming aware of the event, the Contractor must send the Employer's Representative full particulars of the claim.

Party who must act
Contractor
Other party
Engineer
Category
Claim
Trigger type
Event
Period
42 calendar days, after the trigger
Time bar
No
Trigger event
Contractor becomes aware of the event giving rise to the claim
Keys: C confirm, E edit, R reject

Clause 17.2

Particulars of a claim

Within 42 days of becoming aware of the event, the Contractor shall send the Employer's Representative full particulars of the claim.