Clause 5.2

Notify error in Employer's Requirements within 10 days

The Contractor must notify the Employer's Representative within 10 days of finding an error in the Employer's Requirements.

Party who must act
Contractor
Other party
Engineer
Category
Notice
Trigger type
Event
Period
10 calendar days, after the trigger
Time bar
Yes
Trigger event
Contractor finds an error in the Employer's Requirements
Consequence
No right to additional time or money arising from that error
Keys: C confirm, E edit, R reject

Clause 5.2

Errors in the Employer's Requirements

If the Contractor finds an error in the Employer's Requirements, it shall notify the Employer's Representative within 10 days of finding it. A Contractor that does not give this notice in time shall have no right to additional time or money arising from that error.