Clause 5.2
Notify error in Employer's Requirements within 10 days
The Contractor must notify the Employer's Representative within 10 days of finding an error in the Employer's Requirements.
- Party who must act
- Contractor
- Other party
- Engineer
- Category
- Notice
- Trigger type
- Event
- Period
- 10 calendar days, after the trigger
- Time bar
- Yes
- Trigger event
- Contractor finds an error in the Employer's Requirements
- Consequence
- No right to additional time or money arising from that error
Keys: C confirm, E edit, R reject
Clause 5.2
Errors in the Employer's Requirements
If the Contractor finds an error in the Employer's Requirements, it shall notify the Employer's Representative within 10 days of finding it. A Contractor that does not give this notice in time shall have no right to additional time or money arising from that error.