Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 7.1
Give 5 working days' notice before covering work
The Contractor must give the Employer's Representative at least 5 working days' notice before covering any work that is to be inspected.
- Party who must act
- Contractor
- Other party
- Engineer
- Category
- Notice
- Trigger type
- Event
- Period
- 5 working days, before the trigger
- Time bar
- No
- Trigger event
- Covering work that is to be inspected
Keys: C confirm, E edit, R reject
Clause 7.1
Inspection notice
The Contractor shall give the Employer's Representative at least 5 working days' notice before covering any work that is to be inspected.