Demonstration data — not a live contract.
All contracts

Specimen EPC contract

Generic EPC

45 of 45 reviewed

Clause 13.1

Pay advance payment within 30 days

The Employer shall pay the advance payment within 30 days after receiving the Performance Security and the advance payment guarantee.

Party who must act
Employer
Other party
Contractor
Category
Payment
Trigger type
Event
Period
30 calendar days, after the trigger
Time bar
No
Trigger event
Employer receives the Performance Security and the advance payment guarantee
Keys: C confirm, E edit, R reject

Clause 13.1

Advance payment

The Employer shall pay the advance payment within 30 days after receiving the Performance Security and the advance payment guarantee.