Clause 2.1

Give Contractor Site access within 30 days

The Employer must give the Contractor access to the whole of the Site within 30 days after the Commencement Date; otherwise the Contractor may treat the delay as an Employer Delay Event.

Party who must act
Employer
Other party
Contractor
Category
Other
Trigger type
Fixed date
Period
30 calendar days, after the trigger
Time bar
No
Trigger event
Commencement Date
Consequence
Contractor may treat the delay as an Employer Delay Event
Keys: C confirm, E edit, R reject

Clause 2.1

Access to the Site

The Employer shall give the Contractor access to the whole of the Site within 30 days after the Commencement Date. If the Employer has not done so by then, the Contractor may treat the delay as an Employer Delay Event.