Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 3.3
Answer request for decision within 14 days
The Employer's Representative must answer any request for a decision within 14 days of receiving it; a submission not answered within that period is treated as having no objection.
- Party who must act
- Engineer
- Other party
- Contractor
- Category
- Approval
- Trigger type
- Event
- Period
- 14 calendar days, after the trigger
- Time bar
- No
- Trigger event
- Employer's Representative receives a request for a decision
- Consequence
- Submission not answered within the period is treated as having no objection (deemed approval)
Keys: C confirm, E edit, R reject
Clause 3.3
Replies to submissions
The Employer's Representative shall answer any request for a decision within 14 days of receiving it. A submission not answered within that period is treated as having no objection.