Clause 16.1

Notify Force Majeure within 14 days

A Party prevented from performing by Force Majeure shall notify the other Party within 14 days of becoming aware of the event, and shall have no relief for any period before the notice if it does not.

Party who must act
Either party
Other party
Either party
Category
Notice
Trigger type
Event
Period
14 calendar days, after the trigger
Time bar
Yes
Trigger event
Party becomes aware of a Force Majeure event preventing performance
Consequence
No relief for any period before the notice
Keys: C confirm, E edit, R reject

Clause 16.1

Notice of Force Majeure

A Party prevented from performing by Force Majeure shall notify the other Party within 14 days of becoming aware of the event, and shall have no relief for any period before the notice if it does not.