Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 16.1
Notify Force Majeure within 14 days
A Party prevented from performing by Force Majeure shall notify the other Party within 14 days of becoming aware of the event, and shall have no relief for any period before the notice if it does not.
- Party who must act
- Either party
- Other party
- Either party
- Category
- Notice
- Trigger type
- Event
- Period
- 14 calendar days, after the trigger
- Time bar
- Yes
- Trigger event
- Party becomes aware of a Force Majeure event preventing performance
- Consequence
- No relief for any period before the notice
Keys: C confirm, E edit, R reject
Clause 16.1
Notice of Force Majeure
A Party prevented from performing by Force Majeure shall notify the other Party within 14 days of becoming aware of the event, and shall have no relief for any period before the notice if it does not.