Demonstration data — not a live contract.
All contracts

Specimen EPC contract

Generic EPC

45 of 45 reviewed

Clause 17.1

Notify claim for additional time or money within 28 days

If the Contractor considers itself entitled to additional time or money, it shall notify the Employer's Representative within 28 days of becoming aware of the event. If the Contractor does not give notice within that period, it shall lose its right to additional time and money for that event.

Party who must act
Contractor
Other party
Engineer
Category
Claim
Trigger type
Event
Period
28 calendar days, after the trigger
Time bar
Yes
Trigger event
Contractor becomes aware of an event entitling it to additional time or money
Consequence
Loss of right to additional time and money for that event
Keys: C confirm, E edit, R reject

Clause 17.1

Contractor's claims

If the Contractor considers itself entitled to additional time or money, it shall notify the Employer's Representative within 28 days of becoming aware of the event. If the Contractor does not give notice within that period, it shall lose its right to additional time and money for that event.