Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 17.1
Notify claim for additional time or money within 28 days
If the Contractor considers itself entitled to additional time or money, it shall notify the Employer's Representative within 28 days of becoming aware of the event. If the Contractor does not give notice within that period, it shall lose its right to additional time and money for that event.
- Party who must act
- Contractor
- Other party
- Engineer
- Category
- Claim
- Trigger type
- Event
- Period
- 28 calendar days, after the trigger
- Time bar
- Yes
- Trigger event
- Contractor becomes aware of an event entitling it to additional time or money
- Consequence
- Loss of right to additional time and money for that event
Keys: C confirm, E edit, R reject
Clause 17.1
Contractor's claims
If the Contractor considers itself entitled to additional time or money, it shall notify the Employer's Representative within 28 days of becoming aware of the event. If the Contractor does not give notice within that period, it shall lose its right to additional time and money for that event.