Clause 4.4
Notify proposed Subcontractor 21 days before start
The Contractor must notify the Employer's Representative of each proposed Subcontractor at least 21 days before that Subcontractor starts work on the Site.
- Party who must act
- Contractor
- Other party
- Engineer
- Category
- Notice
- Trigger type
- Event
- Period
- 21 calendar days, before the trigger
- Time bar
- No
- Trigger event
- Proposed Subcontractor starts work on the Site
Keys: C confirm, E edit, R reject
Clause 4.4
Subcontractors
The Contractor shall notify the Employer's Representative of each proposed Subcontractor at least 21 days before that Subcontractor starts work on the Site.