Clause 4.4

Notify proposed Subcontractor 21 days before start

The Contractor must notify the Employer's Representative of each proposed Subcontractor at least 21 days before that Subcontractor starts work on the Site.

Party who must act
Contractor
Other party
Engineer
Category
Notice
Trigger type
Event
Period
21 calendar days, before the trigger
Time bar
No
Trigger event
Proposed Subcontractor starts work on the Site
Keys: C confirm, E edit, R reject

Clause 4.4

Subcontractors

The Contractor shall notify the Employer's Representative of each proposed Subcontractor at least 21 days before that Subcontractor starts work on the Site.