Specimen EPC contract

Generic EPC

45 of 45 reviewed

Clause 13.4

Pay certified amount within 45 days

The Employer shall pay each certified amount within 45 days of the date of the certificate.

Party who must act
Employer
Other party
Contractor
Category
Payment
Trigger type
Event
Period
45 calendar days, after the trigger
Time bar
No
Trigger event
Date of the certificate
Keys: C confirm, E edit, R reject

Clause 13.4

Interim payments

The Employer shall pay each certified amount within 45 days of the date of the certificate.