Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 2.2
Provide evidence of funding within 21 days
Within 21 days after a written request from the Contractor, the Employer must provide reasonable evidence that funds are available to pay the Contract Price.
- Party who must act
- Employer
- Other party
- Contractor
- Category
- Submission
- Trigger type
- Event
- Period
- 21 calendar days, after the trigger
- Time bar
- No
- Trigger event
- Written request from the Contractor for evidence of funding
Keys: C confirm, E edit, R reject
Clause 2.2
Evidence of funding
Within 21 days after a written request from the Contractor, the Employer shall provide reasonable evidence that funds are available to pay the Contract Price.