Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 5.1
Submit design delivery schedule within 20 days
The Contractor must submit a design delivery schedule within 20 days after the Commencement Date.
- Party who must act
- Contractor
- Other party
- Employer
- Category
- Programme
- Trigger type
- Fixed date
- Period
- 20 calendar days, after the trigger
- Time bar
- No
- Trigger event
- Commencement Date
Keys: C confirm, E edit, R reject
Clause 5.1
Design programme
The Contractor shall submit a design delivery schedule within 20 days after the Commencement Date.