Clause 10.1
Issue Taking-Over Certificate or give reasons within 21 days
The Employer's Representative must issue the Taking-Over Certificate or give reasons for refusing it within 21 days of receiving the Contractor's application.
- Party who must act
- Engineer
- Other party
- Contractor
- Category
- Completion
- Trigger type
- Event
- Period
- 21 calendar days, after the trigger
- Time bar
- No
- Trigger event
- Employer's Representative receives the Contractor's application for the Taking-Over Certificate
Keys: C confirm, E edit, R reject
Clause 10.1
Taking-Over Certificate
The Employer's Representative shall issue the Taking-Over Certificate or give reasons for refusing it within 21 days of receiving the Contractor's application.