Specimen EPC contract

Generic EPC

45 of 45 reviewed

Clause 11.2

Issue Performance Certificate within 28 days after DNP

The Employer's Representative must issue the Performance Certificate within 28 days after the end of the Defects Notification Period.

Party who must act
Engineer
Other party
Contractor
Category
Defects
Trigger type
Event
Period
28 calendar days, after the trigger
Time bar
No
Trigger event
End of the Defects Notification Period
Keys: C confirm, E edit, R reject

Clause 11.2

Performance Certificate

The Employer's Representative shall issue the Performance Certificate within 28 days after the end of the Defects Notification Period.