Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 12.1
Submit variation proposal within 14 days
Within 14 days of receiving a Variation request, the Contractor must submit a proposal stating its effect on the programme and the Contract Price.
- Party who must act
- Contractor
- Other party
- Employer
- Category
- Variation
- Trigger type
- Event
- Period
- 14 calendar days, after the trigger
- Time bar
- No
- Trigger event
- Contractor receives a Variation request
Keys: C confirm, E edit, R reject
Clause 12.1
Variation proposals
Within 14 days of receiving a Variation request, the Contractor shall submit a proposal stating its effect on the programme and the Contract Price.