Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 8.2
Submit detailed programme within 28 days
The Contractor must submit a detailed programme within 28 days after the Commencement Date.
- Party who must act
- Contractor
- Other party
- Employer
- Category
- Programme
- Trigger type
- Fixed date
- Period
- 28 calendar days, after the trigger
- Time bar
- No
- Trigger event
- Commencement Date
Keys: C confirm, E edit, R reject
Clause 8.2
Programme
The Contractor shall submit a detailed programme within 28 days after the Commencement Date.