Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 5.3
Hand over as-built documents 45 days before Completion Tests
The Contractor must hand over the as-built drawings and operating manuals no later than 45 days before the date of the Completion Tests.
- Party who must act
- Contractor
- Other party
- Employer
- Category
- Submission
- Trigger type
- Event
- Period
- 45 calendar days, before the trigger
- Time bar
- No
- Trigger event
- Date of the Completion Tests
Keys: C confirm, E edit, R reject
Clause 5.3
As-built documents
The Contractor shall hand over the as-built drawings and operating manuals no later than 45 days before the date of the Completion Tests.