Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 8.6
Give 21 days' notice before suspending work
The Contractor must give the Employer at least 21 days' notice before suspending work for non-payment.
- Party who must act
- Contractor
- Other party
- Employer
- Category
- Notice
- Trigger type
- Event
- Period
- 21 calendar days, before the trigger
- Time bar
- No
- Trigger event
- Intention to suspend work for non-payment
Keys: C confirm, E edit, R reject
Clause 8.6
Notice of suspension
The Contractor shall give the Employer at least 21 days' notice before suspending work for non-payment.