Clause 12.2
Object to instruction as Variation within 10 days
A Contractor that considers an instruction to be a Variation must say so in writing within 10 days of receiving it.
- Party who must act
- Contractor
- Other party
- Employer
- Category
- Variation
- Trigger type
- Event
- Period
- 10 calendar days, after the trigger
- Time bar
- Yes
- Trigger event
- Contractor receives an instruction it considers to be a Variation
- Consequence
- The instruction shall be treated as not being a Variation
Keys: C confirm, E edit, R reject
Clause 12.2
Objection to an instruction
A Contractor that considers an instruction to be a Variation shall say so in writing within 10 days of receiving it, failing which the instruction shall be treated as not being a Variation.