Specimen EPC contract
Generic EPC
45 of 45 reviewed
Clause 8.5
Warn of delay within 7 days of learning
The Contractor must warn the Employer's Representative within 7 days of learning of any event likely to delay the Works.
- Party who must act
- Contractor
- Other party
- Engineer
- Category
- Notice
- Trigger type
- Event
- Period
- 7 calendar days, after the trigger
- Time bar
- No
- Trigger event
- Contractor learns of an event likely to delay the Works
Keys: C confirm, E edit, R reject
Clause 8.5
Early warning of delay
The Contractor shall warn the Employer's Representative within 7 days of learning of any event likely to delay the Works.