Clause 8.5

Warn of delay within 7 days of learning

The Contractor must warn the Employer's Representative within 7 days of learning of any event likely to delay the Works.

Party who must act
Contractor
Other party
Engineer
Category
Notice
Trigger type
Event
Period
7 calendar days, after the trigger
Time bar
No
Trigger event
Contractor learns of an event likely to delay the Works