Specimen EPC contract
EPC générique
45 sur 45 revues
Clause 16.1
Notify Force Majeure within 14 days
A Party prevented from performing by Force Majeure shall notify the other Party within 14 days of becoming aware of the event, and shall have no relief for any period before the notice if it does not.
- Partie tenue d’agir
- L’une ou l’autre partie
- Autre partie
- L’une ou l’autre partie
- Catégorie
- Notification
- Type de déclencheur
- Événement
- Délai
- 14 jours calendaires, après le déclencheur
- Forclusion
- Oui
- Événement déclencheur
- Party becomes aware of a Force Majeure event preventing performance
- Conséquence
- No relief for any period before the notice
Touches : C confirmer, E modifier, R rejeter
Clause 16.1
Notice of Force Majeure
A Party prevented from performing by Force Majeure shall notify the other Party within 14 days of becoming aware of the event, and shall have no relief for any period before the notice if it does not.