Specimen EPC contract
EPC générique
45 sur 45 revues
Clause 4.4
Notify proposed Subcontractor 21 days before start
The Contractor must notify the Employer's Representative of each proposed Subcontractor at least 21 days before that Subcontractor starts work on the Site.
- Partie tenue d’agir
- Entrepreneur
- Autre partie
- Maître d’œuvre
- Catégorie
- Notification
- Type de déclencheur
- Événement
- Délai
- 21 jours calendaires, avant le déclencheur
- Forclusion
- Non
- Événement déclencheur
- Proposed Subcontractor starts work on the Site
Touches : C confirmer, E modifier, R rejeter
Clause 4.4
Subcontractors
The Contractor shall notify the Employer's Representative of each proposed Subcontractor at least 21 days before that Subcontractor starts work on the Site.