Specimen EPC contract
EPC générique
45 sur 45 revues
Clause 9.1
Give 21 days' notice of readiness for Tests on Completion
The Contractor must give the Employer's Representative at least 21 days' notice of the date on which it will be ready for the Tests on Completion.
- Partie tenue d’agir
- Entrepreneur
- Autre partie
- Maître d’œuvre
- Catégorie
- Essais
- Type de déclencheur
- Événement
- Délai
- 21 jours calendaires, avant le déclencheur
- Forclusion
- Non
- Événement déclencheur
- Contractor becomes ready for the Tests on Completion
Touches : C confirmer, E modifier, R rejeter
Clause 9.1
Notice of readiness
The Contractor shall give the Employer's Representative at least 21 days' notice of the date on which it will be ready for the Tests on Completion.