Clause 10.1
Issue Taking-Over Certificate or give reasons within 21 days
The Employer's Representative must issue the Taking-Over Certificate or give reasons for refusing it within 21 days of receiving the Contractor's application.
- Partie tenue d’agir
- Maître d’œuvre
- Autre partie
- Entrepreneur
- Catégorie
- Achèvement
- Type de déclencheur
- Événement
- Délai
- 21 jours calendaires, après le déclencheur
- Forclusion
- Non
- Événement déclencheur
- Employer's Representative receives the Contractor's application for the Taking-Over Certificate
Touches : C confirmer, E modifier, R rejeter
Clause 10.1
Taking-Over Certificate
The Employer's Representative shall issue the Taking-Over Certificate or give reasons for refusing it within 21 days of receiving the Contractor's application.