Clause 10.1

Issue Taking-Over Certificate or give reasons within 21 days

The Employer's Representative must issue the Taking-Over Certificate or give reasons for refusing it within 21 days of receiving the Contractor's application.

Partie tenue d’agir
Maître d’œuvre
Autre partie
Entrepreneur
Catégorie
Achèvement
Type de déclencheur
Événement
Délai
21 jours calendaires, après le déclencheur
Forclusion
Non
Événement déclencheur
Employer's Representative receives the Contractor's application for the Taking-Over Certificate
Touches : C confirmer, E modifier, R rejeter

Clause 10.1

Taking-Over Certificate

The Employer's Representative shall issue the Taking-Over Certificate or give reasons for refusing it within 21 days of receiving the Contractor's application.