Clause 5.2
Notify error in Employer's Requirements within 10 days
The Contractor must notify the Employer's Representative within 10 days of finding an error in the Employer's Requirements.
- Partie tenue d’agir
- Entrepreneur
- Autre partie
- Maître d’œuvre
- Catégorie
- Notification
- Type de déclencheur
- Événement
- Délai
- 10 jours calendaires, après le déclencheur
- Forclusion
- Oui
- Événement déclencheur
- Contractor finds an error in the Employer's Requirements
- Conséquence
- No right to additional time or money arising from that error
Touches : C confirmer, E modifier, R rejeter
Clause 5.2
Errors in the Employer's Requirements
If the Contractor finds an error in the Employer's Requirements, it shall notify the Employer's Representative within 10 days of finding it. A Contractor that does not give this notice in time shall have no right to additional time or money arising from that error.