Specimen EPC contract
EPC générique
45 sur 45 revues
Clause 5.3
Hand over as-built documents 45 days before Completion Tests
The Contractor must hand over the as-built drawings and operating manuals no later than 45 days before the date of the Completion Tests.
- Partie tenue d’agir
- Entrepreneur
- Autre partie
- Maître d’ouvrage
- Catégorie
- Remise de document
- Type de déclencheur
- Événement
- Délai
- 45 jours calendaires, avant le déclencheur
- Forclusion
- Non
- Événement déclencheur
- Date of the Completion Tests
Touches : C confirmer, E modifier, R rejeter
Clause 5.3
As-built documents
The Contractor shall hand over the as-built drawings and operating manuals no later than 45 days before the date of the Completion Tests.