Specimen EPC contract
EPC générique
45 sur 45 revues
Clause 11.1
Remedy notified defect within 14 days
The Contractor must remedy any defect notified during the Defects Notification Period within 14 days of the notice.
- Partie tenue d’agir
- Entrepreneur
- Autre partie
- Maître d’ouvrage
- Catégorie
- Malfaçons
- Type de déclencheur
- Événement
- Délai
- 14 jours calendaires, après le déclencheur
- Forclusion
- Non
- Événement déclencheur
- Notice of a defect during the Defects Notification Period
Touches : C confirmer, E modifier, R rejeter
Clause 11.1
Defects Notification Period
The Contractor shall remedy any defect notified during the Defects Notification Period within 14 days of the notice.