Clause 4.2
Extend Performance Security before expiry
Where the Performance Security would expire before the Works are complete, the Contractor must extend it not later than 30 days before its expiry date.
- Partie tenue d’agir
- Entrepreneur
- Autre partie
- Maître d’ouvrage
- Catégorie
- Garantie
- Type de déclencheur
- Événement
- Délai
- 30 jours calendaires, avant le déclencheur
- Forclusion
- Non
- Événement déclencheur
- Expiry date of the Performance Security (where it would expire before completion of the Works)
Touches : C confirmer, E modifier, R rejeter
Clause 4.2
Keeping the security valid
Where the Performance Security would expire before the Works are complete, the Contractor shall extend it not later than 30 days before its expiry date.