Clause 12.2
Object to instruction as Variation within 10 days
A Contractor that considers an instruction to be a Variation must say so in writing within 10 days of receiving it.
- Partie tenue d’agir
- Entrepreneur
- Autre partie
- Maître d’ouvrage
- Catégorie
- Modification
- Type de déclencheur
- Événement
- Délai
- 10 jours calendaires, après le déclencheur
- Forclusion
- Oui
- Événement déclencheur
- Contractor receives an instruction it considers to be a Variation
- Conséquence
- The instruction shall be treated as not being a Variation
Touches : C confirmer, E modifier, R rejeter
Clause 12.2
Objection to an instruction
A Contractor that considers an instruction to be a Variation shall say so in writing within 10 days of receiving it, failing which the instruction shall be treated as not being a Variation.