Specimen EPC contract
EPC générique
45 sur 45 revues
Clause 13.1
Pay advance payment within 30 days
The Employer shall pay the advance payment within 30 days after receiving the Performance Security and the advance payment guarantee.
- Partie tenue d’agir
- Maître d’ouvrage
- Autre partie
- Entrepreneur
- Catégorie
- Paiement
- Type de déclencheur
- Événement
- Délai
- 30 jours calendaires, après le déclencheur
- Forclusion
- Non
- Événement déclencheur
- Employer receives the Performance Security and the advance payment guarantee
Touches : C confirmer, E modifier, R rejeter
Clause 13.1
Advance payment