Specimen EPC contract
EPC générique
45 sur 45 revues
Clause 14.2
Give 28 days' notice to terminate
The Contractor may terminate the Contract by giving 28 days' notice if an amount certified remains unpaid 60 days after it fell due.
- Partie tenue d’agir
- Entrepreneur
- Autre partie
- Maître d’ouvrage
- Catégorie
- Notification
- Type de déclencheur
- Événement
- Délai
- 28 jours calendaires, après le déclencheur
- Forclusion
- Non
- Événement déclencheur
- An amount certified remains unpaid 60 days after it fell due
Touches : C confirmer, E modifier, R rejeter
Clause 14.2
Termination by the Contractor
The Contractor may terminate this Contract by giving 28 days' notice if an amount certified remains unpaid 60 days after it fell due.