Specimen EPC contract
EPC générique
45 sur 45 revues
Clause 12.1
Submit variation proposal within 14 days
Within 14 days of receiving a Variation request, the Contractor must submit a proposal stating its effect on the programme and the Contract Price.
- Partie tenue d’agir
- Entrepreneur
- Autre partie
- Maître d’ouvrage
- Catégorie
- Modification
- Type de déclencheur
- Événement
- Délai
- 14 jours calendaires, après le déclencheur
- Forclusion
- Non
- Événement déclencheur
- Contractor receives a Variation request
Touches : C confirmer, E modifier, R rejeter
Clause 12.1
Variation proposals
Within 14 days of receiving a Variation request, the Contractor shall submit a proposal stating its effect on the programme and the Contract Price.