Specimen EPC contract
EPC générique
45 sur 45 revues
Clause 2.2
Provide evidence of funding within 21 days
Within 21 days after a written request from the Contractor, the Employer must provide reasonable evidence that funds are available to pay the Contract Price.
- Partie tenue d’agir
- Maître d’ouvrage
- Autre partie
- Entrepreneur
- Catégorie
- Remise de document
- Type de déclencheur
- Événement
- Délai
- 21 jours calendaires, après le déclencheur
- Forclusion
- Non
- Événement déclencheur
- Written request from the Contractor for evidence of funding
Touches : C confirmer, E modifier, R rejeter
Clause 2.2
Evidence of funding
Within 21 days after a written request from the Contractor, the Employer shall provide reasonable evidence that funds are available to pay the Contract Price.