Specimen EPC contract

EPC générique

45 sur 45 revues

Clause 2.2

Provide evidence of funding within 21 days

Within 21 days after a written request from the Contractor, the Employer must provide reasonable evidence that funds are available to pay the Contract Price.

Partie tenue d’agir
Maître d’ouvrage
Autre partie
Entrepreneur
Catégorie
Remise de document
Type de déclencheur
Événement
Délai
21 jours calendaires, après le déclencheur
Forclusion
Non
Événement déclencheur
Written request from the Contractor for evidence of funding
Touches : C confirmer, E modifier, R rejeter

Clause 2.2

Evidence of funding

Within 21 days after a written request from the Contractor, the Employer shall provide reasonable evidence that funds are available to pay the Contract Price.