Demonstration data — not a live contract.
All contracts

Specimen EPC contract

Generic EPC

8.2 Submit detailed programme within 28 days

The Contractor must submit a detailed programme within 28 days after the Commencement Date.

  1. Oct 13, 2026

    Trigger: Commencement Date

  2. Oct 29, 2026

    Outgoing Detailed programme for review, OUT-0001 (Satisfies)

  3. Nov 10, 2026

    Due dateMet

    28 calendar days after the event, not counting the day of the event.