Demonstration data — not a live contract.
All contracts

Specimen EPC contract

Generic EPC

12.2 Object to instruction as Variation within 10 days

A Contractor that considers an instruction to be a Variation must say so in writing within 10 days of receiving it.

  1. Oct 24, 2026

    Trigger: Variation request received

  2. Nov 3, 2026

    Due dateOverdue

    10 calendar days after the event, not counting the day of the event.