Specimen EPC contract
Generic EPC
17.2 Send full particulars of claim within 42 days
Within 42 days of becoming aware of the event, the Contractor must send the Employer's Representative full particulars of the claim.
Oct 30, 2026
Trigger: Late delivery of Employer-supplied plant
Dec 11, 2026
Due dateOpen
42 calendar days after the event, not counting the day of the event.