Specimen EPC contract
Generic EPC
8.3 Deliver progress report every 30 days
The Contractor must deliver a progress report to the Employer's Representative every 30 days until the Works are taken over.
Oct 13, 2026
Trigger: Commencement Date
Nov 12, 2026
Due dateOpen
Every 30 days, occurrence 1.
Dec 12, 2026
Due dateOpen
Every 30 days, occurrence 2.
Jan 11, 2027
Due dateOpen
Every 30 days, occurrence 3.
Feb 10, 2027
Due dateOpen
Every 30 days, occurrence 4.
Mar 12, 2027
Due dateOpen
Every 30 days, occurrence 5.
Apr 11, 2027
Due dateOpen
Every 30 days, occurrence 6.
May 11, 2027
Due dateOpen
Every 30 days, occurrence 7.
Jun 10, 2027
Due dateOpen
Every 30 days, occurrence 8.
Jul 10, 2027
Due dateOpen
Every 30 days, occurrence 9.
Aug 9, 2027
Due dateOpen
Every 30 days, occurrence 10.
Sep 8, 2027
Due dateOpen
Every 30 days, occurrence 11.
Oct 8, 2027
Due dateOpen
Every 30 days, occurrence 12.
Nov 7, 2027
Due dateOpen
Every 30 days, occurrence 13.
Dec 7, 2027
Due dateOpen
Every 30 days, occurrence 14.
Jan 6, 2028
Due dateOpen
Every 30 days, occurrence 15.
Feb 5, 2028
Due dateOpen
Every 30 days, occurrence 16.
Mar 6, 2028
Due dateOpen
Every 30 days, occurrence 17.
Apr 5, 2028
Due dateOpen
Every 30 days, occurrence 18.