Specimen EPC contract
Generic EPC
8.5 Warn of delay within 7 days of learning
The Contractor must warn the Employer's Representative within 7 days of learning of any event likely to delay the Works.
Oct 30, 2026
Trigger: Late delivery of Employer-supplied plant
Nov 6, 2026
Due dateOpen
7 calendar days after the event, not counting the day of the event.