17.1 Notify claim for additional time or money within 28 days
If the Contractor considers itself entitled to additional time or money, it shall notify the Employer's Representative within 28 days of becoming aware of the event. If the Contractor does not give notice within that period, it shall lose its right to additional time and money for that event.
Oct 30, 2026
Trigger: Late delivery of Employer-supplied plant
Nov 27, 2026
Due dateOpen
28 calendar days after the event, not counting the day of the event.