Specimen EPC contract

Generic EPC

8.1 Begin Works within 14 days of Commencement Date

The Contractor must begin the Works within 14 days after the Commencement Date.

  1. Oct 13, 2026

    Trigger: Commencement Date

  2. Oct 27, 2026

    Due dateOverdue

    14 calendar days after the event, not counting the day of the event.