Specimen EPC contract
EPC générique
8.5 Warn of delay within 7 days of learning
The Contractor must warn the Employer's Representative within 7 days of learning of any event likely to delay the Works.
30 oct. 2026
Déclencheur : Late delivery of Employer-supplied plant
6 nov. 2026
ÉchéanceOuverte
7 jours calendaires après l'événement, sans compter le jour de l'événement.